Solar Photovoltaic (PV) Development, Engineering, Procurement and Construction (EPC) and Grid Analysis

Dimensions & Physics

Array Hierarchy (String)

Module Logistics

Baseline Project Economics
Year 1 Revenue Projection£0
25 Year Revenue Projection£0
35 Year Revenue Projection£0
Total CAPEX£0
CAPEX per Wp£0.00/Wp
Undiscounted 25 Year Cash Surplus£0
Undiscounted 35 Year Cash Surplus£0

Revenue

Development Financials

Development Capital at Risk£0
Module Supply Cost£0
EPC Cost£0
Other Owner Costs£0
Grid Connection Cost£0
Total Build Cost£0
Target Exit Value£0
Operating Asset Net Present Value (NPV)£0
Gross Development Margin£0
Risk Adjusted Development Value£0
Development Equity Money Multiple0.00x

CAPEX

Loss Allowances

BESS Optional

Dimensions & Physics

Array Hierarchy (Central)

A skid is a factory assembled power package. It usually combines inverter equipment, transformer, switchgear, protection and auxiliary systems on a transportable base or frame. Finance and non technical teams can treat each skid as one repeatable cost and power block. Values above 10 MWac should be treated as large power block assumptions and require transformer, MV switchgear, harmonic, thermal, protection and grid code verification.

Module Logistics

Baseline Project Economics
Year 1 Revenue Projection£0
25 Year Revenue Projection£0
35 Year Revenue Projection£0
Total CAPEX£0
CAPEX per Wp£0.00/Wp
Undiscounted 25 Year Cash Surplus£0
Undiscounted 35 Year Cash Surplus£0

Revenue

Development Financials

Development Capital at Risk£0
Module Supply Cost£0
EPC Cost£0
Other Owner Costs£0
Grid Connection Cost£0
Total Build Cost£0
Target Exit Value£0
Operating Asset Net Present Value (NPV)£0
Gross Development Margin£0
Risk Adjusted Development Value£0
Development Equity Money Multiple0.00x

CAPEX

Loss Allowances

BESS Optional

Selected Grid Node

Substation:None selected
Voltage:Unknown
Longitude:n/a
Latitude:n/a

Technical Quantity Summary

Total Module Count:0
Total DC Capacity:0.00 MWp
Implied AC Capacity:0.00 MWac
DC/AC Ratio:1.20
String Inverter Rating:n/a
Inverter ACmax per Skid:0.00 MVA
Skid Transformer Rating:0.00 MVA
33 kV Ring Main AC Rating:0.00 MVA
Engineering Warning:Check assumptions
Net Module Surface Area:0 Acres
Net Array Area at GCR:0 Acres
Indicative Gross Site Area:0 Acres
Modules per Packing Unit:0
Total Packing Units:0
Modules per Container:0
Total Base Containers:0
Spare Module Allowance:0%
Containers (Inc. Spares):0
Containers per MWp:0.00

Custom Reference Benchmark

Implied Benchmark:~ 1,500 modules/MW
ENGINEERING SCREENING OUTPUT

These outputs are indicative screening values only. They are not construction design, financial advice, EPC pricing, grid compliance, logistics planning or transport instruction. All quantities, packaging, site area, cable routes, container loads, module specifications and financial assumptions must be verified against current manufacturer datasheets, project specific drawings, EPC scope, grid requirements and competent engineering review.

Electrical Topology Explanation

A string is a series chain of PV modules. For example, 30 modules per string means the voltage of 30 modules is added before entering the inverter.

A string inverter converts DC power from several PV strings into low voltage AC power. The inverter rating in kVA defines the apparent AC power capability of each inverter. For example, 28 string inverters rated at 352 kVA create a skid block of approximately 9,856 kVA before transformer and grid limitations.

A skid is the local electrical station that collects power from a group of inverters. It normally includes low voltage AC switchgear, a step up transformer, protection equipment and a medium voltage connection, often at 33 kV.

A Ring Main Unit, or RMU, is medium voltage switchgear used to connect skids into a 33 kV network. It normally includes cable switches, protection, earthing switches and sometimes transformer protection.

A 33 kV ring main is a medium voltage collection circuit that links several skids back toward the main substation or HV station. In this sandbox, Skids per 33 kV Ring Main means how many local substations sit on each medium voltage collection circuit. Number of 33 kV Ring Main Circuits means how many separate collection circuits are used across the solar farm.

The financial model is driven by this hierarchy. More modules, strings, inverters, substations and 33 kV ring circuits change DC capacity, AC capacity, site area, cable loading, losses, CAPEX, revenue and development value. If the topology assumptions are unrealistic, the financial outputs will also be unrealistic.

About the VENTUS GIS SLD Sandbox

VENTUS GIS SLD Sandbox is a working engineering screening tool for utility scale solar, storage and grid connection analysis.

The tool helps users explore the relationship between land, grid proximity, solar topology, module count, inverter architecture, logistics, BESS assumptions and baseline project economics in one visual interface.

Users can enter a location, view UK substation reference data, select a grid node and generate an indicative solar layout using either string inverter or central inverter topology. The tool can estimate module count, DC capacity, AC capacity, site area, packing units, container loads, baseline revenue, CAPEX assumptions and simple long term financial outputs.

This is a real engineering screening tool. It is not a final construction design package, grid offer, connection approval, EPC quotation or financial advice. It is designed to support early stage project assessment by making technical, spatial, logistics and financial assumptions visible before deeper engineering, grid, planning, procurement and financial studies begin.

A key feature of the sandbox is that technical and commercial assumptions are shown together. In real projects, module count becomes logistics. Cable routing becomes electrical loss. Grid proximity becomes interface risk. BESS assumptions affect land, CAPEX and revenue logic. Financial outputs only become useful when the physical assumptions behind them are visible.

The tool also includes GeoJSON export so that generated layouts and assumptions can be carried into external GIS workflows, reports, internal review or further engineering discussion. The exported data is intended to preserve context, including topology mode, technical assumptions, logistics assumptions, financial assumptions and warnings.

The public substation layer is reference data only. A visible substation point does not confirm available capacity, connection rights, voltage suitability, cable route, grid acceptance or point of connection approval. Any real project must still be reviewed by competent engineers, grid specialists, planners, EPC teams, legal advisers and project finance professionals before real world decisions are made.

VENTUS created this sandbox to support better early stage thinking in solar and storage deployment. The aim is to help developers, engineers, suppliers, investors and commercial teams ask better questions before committing time, capital and contractual responsibility.

Use the sandbox as a thinking tool. Use it to test scale. Use it to compare assumptions. Use it to understand where deeper engineering begins.

Financial Model Logic

The financial model is a screening layer for Solar Photovoltaic (PV) development, grid connection, Engineering, Procurement and Construction (EPC) readiness and operating asset value. It is designed to make the main commercial assumptions visible beside the physical layout, not to replace a full valuation report or investment committee model.

The energy price input is a blended screening assumption. It may represent government backed price stabilisation, a private buyer contract, merchant power exposure or a blended revenue case. Users should enter the expected captured electricity price that best reflects the project route to market.

The Operating Asset Net Present Value (NPV) input is user editable because operational value changes with contract quality, revenue certainty, merchant exposure, grid status, asset maturity, inflation, debt assumptions and investor return requirements. A project with stable long term revenue may justify a higher value assumption than a project with greater merchant exposure.

The development cost per Megawatt (MW) input is user editable because development capital at risk rises as a project moves from site identification through grid review, planning, buyer or revenue agreement review, technical design and Engineering, Procurement and Construction (EPC) readiness.

The Target Exit Value input is a screening assumption, not a promised sale value or formal valuation. It helps users test whether there may be development margin after development cost, module supply cost, Engineering, Procurement and Construction (EPC) cost, grid connection cost and owner costs.

The model deliberately avoids pretending to be a full discounted cash flow model. It is a fast comparison tool for early stage decision making. Real projects still require competent engineering, grid studies, planning review, legal review, tax review, debt sizing, revenue analysis and investment committee approval.

Detailed Screening Disclaimer

The VENTUS GIS SLD Sandbox is provided as an early stage screening, learning and project qualification tool. It is intended to help users visualise relationships between land, grid proximity, solar topology, cable route assumptions, module count, inverter architecture, logistics, Battery Energy Storage System (BESS) assumptions, capital cost assumptions, revenue assumptions and indicative project economics.

The sandbox does not create, imply or evidence a grid offer, grid connection approval, point of connection approval, available grid capacity, land right, wayleave, easement, planning consent, EPC price, construction programme, investment recommendation, financial valuation, lending approval or insurance acceptance.

Public substation points, voltage references and grid node markers are reference data only. A visible substation point does not confirm voltage suitability, thermal capacity, fault level headroom, protection compatibility, connection queue status, Gate 2 eligibility, land access, constructability, outage availability, reinforcement cost or acceptance by a Distribution Network Operator (DNO), Transmission Owner (TO), National Energy System Operator (NESO) or any other network party.

User drawn cable routes, pin routes, direct route lines and exported route geometries are indicative routing assumptions only. They do not confirm landowner consent, wayleaves, easements, highway rights, railway crossings, watercourse crossings, third party utility conflicts, environmental constraints, planning acceptability, installation method, cable pulling feasibility, trench design, duct design, joint bay location, thermal rating, voltage drop, losses, protection design, earthing design or final constructability.

All cable lengths, losses and route assumptions must be checked by competent cable engineers using project specific route surveys, cable data sheets, soil thermal resistivity, installation depth, grouping factors, duct factors, cyclic loading, conductor temperature limits, voltage drop limits, short circuit withstand, sheath bonding, earthing design, protection settings and applicable standards before procurement or construction decisions are made.

Solar layout outputs are indicative. Module count, DC capacity, AC capacity, site area, Ground Coverage Ratio (GCR), gross site factor, block layout, inverter count, substation count, access assumptions and container quantities must be verified against manufacturer datasheets, planning drawings, topographical surveys, geotechnical surveys, environmental constraints, drainage strategy, fire access, operations access, EPC scope, grid compliance requirements and final design drawings.

Financial outputs are screening values only. Revenue, capital expenditure, development cost, module cost, EPC cost, owner cost, grid connection cost, operating cost, target exit value, Operating Asset Net Present Value (NPV), development margin and surplus outputs depend on assumptions entered by the user and may change materially with route to market, Contracts for Difference (CfD), Power Purchase Agreement (PPA), merchant exposure, curtailment, grid charges, inflation, interest rates, debt sizing, tax treatment, construction cost, contingencies, warranties, insurance and investor return requirements.

BESS assumptions are indicative only. BESS power, BESS energy, BESS CAPEX, cycles, efficiency and revenue per MWh do not replace battery degradation modelling, augmentation strategy, warranty review, revenue stack modelling, fire safety review, planning review, grid compliance studies, metering design, controls design, availability assumptions, insurance review or safety case preparation.

The GeoJSON export preserves useful context for review and discussion, but exported data is not an Issued for Construction (IFC) drawing, legal boundary plan, grid application pack, cable route schedule, bill of quantities, EPC instruction, investment memorandum or bankable technical due diligence package. Any exported file must be reviewed and validated before being used in external GIS workflows, reports, procurement discussions, investor presentations or professional advice.

Users remain responsible for checking all inputs, outputs, assumptions and exported data. Any real world project should be reviewed by competent engineers, grid specialists, planners, environmental consultants, land agents, legal advisers, tax advisers, insurance advisers, EPC contractors, Owner's Engineers, lenders and investment committee professionals before committing capital, signing contracts, placing orders or making public claims.

The sandbox is designed to make assumptions visible, not to remove professional judgement. It should be used to ask better questions, compare scenarios, identify where deeper work is required and support disciplined early stage decision making.