LV AC and DC Distribution Cables Price Estimator

Large scale price estimator for Low Voltage (LV) Alternating Current (AC) and Direct Current (DC) cables. These form the electrical backbone of Solar PV arrays, BESS installations, and standard distribution networks.


Market Inputs

Parameter Value
LME Copper (USD) USD 14,575 / tonne
LME Aluminium (USD) USD 3,763 / tonne
Exchange Rates 1 GBP = 1.3463 USD
1 GBP = 1.1575 EUR
Copper (GBP) GBP 10,826 / tonne
Aluminium (GBP) GBP 2,795 / tonne
Copper (EUR) EUR 12,531 / tonne
Aluminium (EUR) EUR 3,235 / tonne
Last Update Wednesday 03 June 2026 11:08 UTC

Weight Formulas & Pricing Rule


LV / DC Main Cables (Aluminium)

Typical single core aluminium distribution cables.

Conductor (mm²) Aluminium (kg/km) Metal Value (GBP/km) Net Price (GBP/km) Net Price (EUR/km)
95 277.4 775 3,877 4,488
120 350.4 979 4,897 5,669
150 438.0 1,224 6,122 7,086
185 540.2 1,510 7,550 8,739
240 700.8 1,959 9,795 11,337
300 876.0 2,449 12,243 14,171
400 1,168.0 3,265 16,324 18,895
500 1,460.0 4,081 20,405 23,619
630 1,839.6 5,142 25,711 29,760

LV Distribution Cables (Copper)

Typical single core copper distribution cables.

Conductor (mm²) Copper (kg/km) Metal Value (GBP/km) Net Price (GBP/km) Net Price (EUR/km)
16 153.6 1,663 5,543 6,416
25 240.0 2,598 8,661 10,025
35 336.0 3,637 12,125 14,034
50 480.0 5,196 17,321 20,049
70 672.0 7,275 24,250 28,069
95 912.0 9,873 32,911 38,093
120 1,152.0 12,471 41,571 48,118
150 1,440.0 15,589 51,964 60,147
185 1,776.0 19,227 64,089 74,182
240 2,304.0 24,943 83,142 96,236
300 2,880.0 31,178 103,928 120,295
400 3,840.0 41,571 138,571 160,393

Notes

Estimates are DAP (Delivered at Place) for large-scale utility procurement. Values do not represent small-batch wholesale counter prices. Final prices vary based on formal manufacturer negotiations and hedging contracts against copper, aluminium, polymers, energy costs, shipping, currency exchange rates and engineering sign off on appropriate materials selection. Price is inflated slightly to counter procurement risks but nothing is guaranteed until contract signature and payment terms agreement with suppliers and appropriate insurance against force majeure.